Cannon House Service Rebuild

Coordination schedules to facilitate an outage.

Aug 24, 2009

© Zorko Electric

Zorko Electric worked with D Square Energy and Seattle City Light to coordinate an entire facility shutdown of a nursing home in Seattle, Washington.  A need to increase service capacity required a new service to be built alongside the existing live service.  The generator supplying required emergency loads was also fed into the new ATS switches feeding the required safety systems in the building.  Power switchover was done in one day. 